*Pages 1--5 from Microsoft Word - 53453.doc* PUBLIC NOTICE Federal Communications Commission 445 12 th St., S. W. Washington, D. C. 20554 News Media Information 202 / 418- 0500 Internet: http:// www. fcc. gov TTY: 1- 888- 835- 5322 DA 05- 3134 December 2, 2005 WIRELESS TELECOMMUNICATIONS BUREAU ANNOUNCES THAT 800 MHZ BAND RECONFIGURATION WILL COMMENCE JANUARY 3, 2006, IN THE NPSPAC REGIONS ASSIGNED TO WAVE 3 WT Docket No. 02- 55 In July 2004, the Federal Communications Commission (Commission) adopted a Report and Order in this docket which, inter alia, reconfigured the 800 MHz band to eliminate interference to public safety and other land mobile communication systems operating in the band. 1 As specified in the Report and Order, the band reconfiguration process is being overseen by a Transition Administrator (TA) 2 which has provided the Commission with a plan detailing when band reconfiguration will commence in each of the fifty- five 800 MHz National Public Safety Planning Advisory Committee (NPSPAC) regions. 3 On March 11, 2005, the Bureau approved the TA’s basic 800 MHz band reconfiguration schedule, i. e., the grouping of the NPSPAC regions into four waves (Waves 1- 4) and starting the reconfiguration process in each wave on the dates recommended by the TA. 4 1 See Improving Public Safety Communications in the 800 MHz Band, Report and Order, WT Docket No. 02- 55, 19 FCC Rcd 14969 (2004) (Report and Order). See also Supplemental Order and Order on Reconsideration, WT Docket No. 02- 55, 19 FCC Rcd 25120 (2004) (Supplemental Order). See also, Memorandum Opinion and Order, WT Docket No. 02- 55, FCC 05- 174, released October 5, 2005. 2 The Transition Administrator was recommended by a search committee made up of representatives of the five major stakeholders in the 800 MHz band, Nextel Communications, Inc. (Nextel), the Association of Public Safety Communications Officials- International (APCO), the Industrial Telecommunications Association (ITA), Southern LINC and the United Telecom Council (UTC). See Report and Order, 19 FCC Rcd at 15070- 75 ¶¶ 190- 200. The Bureau concurred in the search committee’s recommendation that the Transition Administrator be comprised of a three- organization team made up of BearingPoint, Squire- Sanders- Dempsey LLP, and Baseline Telecom, Inc. See Wireless Telecommunications Bureau Concurs with Search Committee Selection of a Transition Administrator, Public Notice, 19 FCC Rcd 21923 (WTB, PSCID 2004). Additional information on the TA can be found on its web page – www. 800ta. org. 3 On January 31, 2005, the TA filed a plan containing a general schedule for implementing 800 MHz band reconfiguration. See Regional Prioritization Plan of the 800 MHz Transition Administrator, WT Docket No. 02- 55, filed January 31, 2005 (TA Plan). The TA later amended the plan to specify a date certain for commencement of Wave 4. See letter dated February 18, 2005, from Robert B. Kelly, Squire, Sanders & Dempsey to Michael J. Wilhelm Chief, Public Safety and Critical Infrastructure Division, Wireless Telecommunications Bureau, FCC. The TA’s band reconfiguration schedule may be viewed at www. 800ta. org. 4 See Wireless Telecommunications Bureau Approves the Basic Reconfiguration Schedule Put Forth in the Transition Administrator’s 800 MHz Regional Prioritization Plan, Public Notice, 20 FCC Rcd 5159, (WTB 2005) (TA Plan PN). 1 2 As part of the 800 MHz band reconfiguration process, the Commission stated that it would issue a Public Notice thirty days before reconfiguration is scheduled to start in each NPSPAC region. 5 Each such Public Notice specifies a three- month voluntary negotiation period during which time identified licensees in the regions being reconfigured are encouraged to reach agreement with Nextel on the details of relocating. 6 The voluntary negotiation period is followed by a three- month mandatory negotiation period, if necessary. 7 The Commission also stated that it would freeze the filing of certain 800 MHz applications for the regions being reconfigured when it issued a Public Notice announcing the date when voluntary negotiation of relocation agreements must be concluded. 8 The Commission explained that this freeze is necessary in order to maintain a stable spectral landscape during the reconfiguration process in each region. 9 The Commission delegated authority to issue these Public Notices to the Public Safety and Critical Infrastructure Division of the Wireless Telecommunications Bureau (WTB). 10 On May 27, 2005, WTB released a Public Notice announcing the reconfiguration start date for the NPSPAC regions assigned to Wave 1 (for the non- NPSPAC channels therein). 11 This Wave 1 PN also specified the 800 MHz reconfiguration benchmark compliance dates. 12 On September 2, 2005, WTB released a Public Notice announcing the reconfiguration start date for NPSPAC regions assigned to Wave 2 (non- NPSPAC channels). 13 By this Public Notice, we announce that the 800 MHz band reconfiguration process for non- NPSPAC channels will start January 3, 2006, in the NPSPAC regions assigned to Wave 3. 14 A list of NPSPAC regions assigned to Wave 3 is attached to this Public Notice. 15 The three- month 5 See 47 C. F. R § 90. 677( b) and Report and Order, 19 FCC Rcd 15076 ¶ 201. See also TA Plan PN at 2. 6 See 47 C. F. R. § 90. 677( b). 7 See 47 C. F. R. § 90. 677( c). 8 See Report and Order, 19 FCC Rcd 15078 ¶ 204. 9 See id. See also Supplemental Order, 19 FCC Rcd 25158- 59 ¶ 87. The Bureau has provided additional information regarding the processing of 800 MHz applications during reconfiguration and indicated that there will be two separate application filing freezes for each region, one filing freeze for non- NPSPAC licensees and a separate freeze for NPSPAC licensees. See Wireless Telecommunications Bureau Outlines Application Freeze Process for Implementation of 800 MHz Band Reconfiguration, Public Notice, 20 FCC Rcd 8905 (WTB 2005) (Two Freeze PN). 10 See Report and Order, 19 FCC Rcd 15076 ¶ 201. 11 See Wireless Telecommunications Bureau Announces that 800 MHz Band Reconfiguration Will Commence June 27, 2005, in the NPSPAC Regions Assigned to Wave 1 and Specifies 800 MHz Reconfiguration Benchmark Compliance Dates, Public Notice, 20 FCC Rcd 9961 (WTB 2005) (Wave 1 PN). 12 See id. at 3. Nextel must (1) relocate all but Nextel and SouthernLINC incumbents from Channels 1- 120 in the first twenty NPSPAC regions scheduled for reconfiguration and (2) initiate retuning negotiations with all NPSPAC licensees in these same regions by December 26, 2006 (eighteen month benchmark). Further, all applicable systems must have commenced reconfiguration by December 26, 2007 (thirty month benchmark). The 800 MHz band reconfiguration must be completed by June 26, 2008 (thirty- six month benchmark). Id. 13 See Wireless Telecommunications Bureau Announces that 800 MHz Band Reconfiguration Will Commence October 3, 2005, in the NPSPAC Regions Assigned to Wave 2, Public Notice, DA 05- 2390, released September 2, 2005 (Wave 2 PN). 14 For the purposes of this Public Notice, non- NPSPAC channels are those channels in the 806- 817/ 851- 862 MHz band. For the purposes of reconfiguration, this group generally will consist of 800 MHz band licensees on Channels 1- 120 (806- 809/ 851- 854 MHz). 2 4 The Commission’s Universal Licensing System (ULS) will automatically update modification applications filed to implement 800 MHz band reconfiguration to show the appropriate new radio service code (i. e., applicants should file using their current radio service codes). Once the radio service code has been changed on the license by the Commission, licensees filing subsequent applications concerning that license must use the new radio service code. The Reconfiguration Plan filed by the TA is available on the Commission’s 800 MHz band reconfiguration web page at http:// www. 800MHz. gov. Questions concerning the plan, and other Transition Administrator matters, including whether your 800 MHz system must be relocated, should be directed to Brett Haan, BearingPoint, 1676 International Drive, McLean, VA 22102, Brett. Haan@ 800ta. org. For additional information on 800 MHz band reconfiguration issues, generally, please contact Roberto Mussenden, Esq., Public Safety and Critical Infrastructure Division, Wireless Telecommunications Bureau, at (202) 418- 0680, TTY (202) 418- 7233, or via e- mail to Roberto. Mussenden@ fcc. gov. Action by the Chief, Public Safety and Critical Infrastructure Division, Wireless Telecommunications Bureau. – FCC – 4 5 APPENDIX NPSPAC Regions Assigned to Wave 3 NPSPAC Region 1 Description of Region 2 1 Alabama 9 Florida 10 Georgia 18 Louisiana 23 Mississippi 31 North Carolina 37 South Carolina * Large non- public safety systems that cover multiple NPSPAC regions 3 1 Per the TA’s request, we moved the Louisiana NPSPAC region (# 18) from Wave 2 to Wave 3. See letter from Bob Kelly to Michael Wilhelm, Chief Public Safety and Critical Infrastructure Division, dated September 2, 2005. 2 Regions that are only a portion of a state or states are defined by counties. A list of the counties in each of these regions can be accessed at http:// www. fcc. gov/ Bureaus/ Wireless/ Orders/ 1998/ fcc98191. txt. 3 Large non- public safety systems that had no systems in Wave 1 or 2 and that provide coverage beyond the border of NPSPAC regions in Wave 3 will commence reconfiguration of their entire system, including base stations located outside the boundaries of Wave 3 NPSPAC regions, as part of the Wave 3 reconfiguration process. 5